Projects and cost estimates
The availability of adequate funding to realise transport projects listed in this report remain a grave concern for the municipality. Table 12 below shows the list of projects and required funding. The main sources of funding with be from the municipal budget as allocated in the IDP as well as through MIG funding applications. Funding should also be agreed with iLembe DM as well as KZN DoT.
Table 12: Project list and Funding requirements
Description | Funding Requirement | Funding Allocation |
Intermodal hub as part of urban regeneration program | R240.0m | IDP |
Upgrading of Ballito taxi rank | R21.5m | IDP |
Planning of high-quality trunk bus service | R7.5m | No allocation |
Planning of feeder and distribution service for trunk system and associated infrastructure | R5.0m | No allocation |
Planning of the Doornkop PT facility | R1.5m | No allocation |
Development of a NMT plan for the municipality | R1.0m | No allocation |
Development of a revival plan for rail service | R1.0m | No allocation |
Development of a Universal Access plan for PT services and infrastructure | R1.0m | No allocation |
Road upgrading, maintenance and building of new roads | R33.0m | IDP |
Planning and improvement of traffic signal system for the town of KwaDukuza | R3.0m | No allocation |